CAT 2022 Slot 3 Question 1- Bob can finish a job in 40 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three-day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is
Explanation

CAT 2022 Slot 3 Question 2-
A group of N
people worked on a project. They finished 35%
of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N
is
A.23
B.140
C.36
D.150
Explanation
N people finish 35% of the project by working 7 hours a day for 10 days.
N people finish 35% of the project by working 70 hours.
N people finish 5% of the project by working 10 hours.
N people finish 65% of the project by working 130 hours.
65% of the project is done in N * 130 man hours.
The remaining 65% was actually done by (N-10) people in 14 days by working 10 hours a day.
(N-10) people finish 65% of the project by working 140 hours.
65% of the project is done in (N – 10) * 140 man hours.
N * 130 = (N – 10) * 140
13N = 14N – 140
N = 140
CAT 2022 Slot 2 Question 3-
Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is
Explanation
Time taken by Anu, Tanu and Manu to complete a job is in the ratio 5 : 8 : 10
This means that their efficiencies are in the ratio 1/5:1/8:1/10
Or, their efficiencies are in the ratios 8 : 5 : 4
This means, for instance, if Anu can wash 8 plates in an hour, Tanu and Manu can wash 5 & 4 plates respectively in one hour.
So, let us remodel the entire question over this imaginary scenario of washing plates…
All three of them finish the job in 4 days working 8 hours per day.
Anu, Tanu and Manu can wash 8, 5 and 4 plates respectively in an hour.
So the total number of plates = (8+5+4)×4×8=17×4×8
Anu and Tanu work together for 6 days, working 6 hours 40 minutes per day.
The total number of plates washed by them = (8+5)×6×6*2/3=13×40
So the remaining plates to be washed =17×4×8−13×40
=4(17×8−130)
=4(80+56−130)
=4×6
So, the question is, in how man hours can Manu wash 4×6
plates?
We know that Manu can wash 4 plates in one hour.
Therefore, he requires 6 hours to wash 4×6
plates.
The answer is ‘6’
CAT 2021 Slot 3 Question 3- Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is
Explanation

CAT 2021 Slot 3 Question 4-
One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is
A.12
B.11.5
C.12.5
D.10
Explanation
Let R be the fraction of work done by Rahul in 1 hour.
and G be the fraction of work done by Gautam in 1 hour.
Initially Rahul works from 9AM to 5PM (8 hours) and Gautam works for 2 hours less.
8R + 6G = 1 whole unit of work
If they start together they finish 30 minutes earlier or if they start at 9 AM, they finish at 4:30PM (7.5 hours)
7.5R + 7.5G = 1 whole unit of work
8R + 6G = 7.5R + 7.5G
0.5R = 1.5G
R = 3G
This means Rahul is thrice as efficient as Gautam.
8R + 6G = 1 whole unit of work
8R + 2R = 1 whole unit of work
10R = 1 whole unit of work
R is the fraction of work done by Rahul in 1 hour.
Since 10R = 1
R alone takes 10 hours to finish the job.
CAT 2021 Slot 2 Question 5-
Anil can paint a house in 60 days while Bimal can paint it in 84 days. Anil starts painting and after 10 days, Bimal and Charu join him. Together, they complete the painting in 14 more days. If they are paid a total of ₹ 21000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is
A.9000
B.9100
C.9200
D.9150
Explanation

CAT 2021 Slot 2 Question 6-
Two pipes A and B are attached to an empty water tank. Pipe A fills the tank while pipe B drains it. If pipe A is opened at 2 pm and pipe B is opened at 3 pm, then the tank becomes full at 10 pm. Instead, if pipe A is opened at 2 pm and pipe B is opened at 4 pm, then the tank becomes full at 6 pm. If pipe B is not opened at all, then the time, in minutes, taken to fill the tank is
A.140
B.120
C.144
D.264
Explanation
Let the filling rate of pipe A be ‘a’ and the rate of emptying the tank of pipe B be ‘b’.
Then from the given information we can say that, when pipe A is kept open from 2PM to 10PM, i.e. for 8 hours and pipe B drains from 3PM till 10PM (7 hours), the tank gets filled up.
So,
8a – 7b = 1 [1]
Also, from the second statement,
A is kept open from 2 PM to 6 PM (4 hours), and B is kept open for 2 hours (4 PM to 6PM), the tank gets filled up.
4a – 2b = 1 [2]
Multiplying equation [2] and subtracting [1] from it we get
8a – 4b – (8a – 7b) = 2 – 1
7b – 4b = 1
b = 1/3
From here we can compute the value of a
Putting the value of b in eq [2]
4a – 2(1/3) = 1
4a – 2/3 = 1
4a = 1 + 2/3
4a = 5/3
a = 5/12
Hence the rate of filling is 5/12.
If only pipe a is kept open, the tank will get filled in, say ‘n’ hours
n a = 1
n (5/12) = 1
So, n = 12/5
= 2.4 hours
= 144 minutes
CAT 2021 Slot 1 Question 7-
Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is
Explanation
Let’s consider the efficiencies of Amar, Akbar, and Anthony to be x, y, z respectively.
x + y = 1/12
y + z = 1/16
z + x = 1/24
If we add the above equations, we will get 2(x + y + z) = 3/16
x + y + z = 3/32
From the above equations, we can get x = 1/32
, y = 5/96
, z = 1/96
Hence, x is neither the fastest nor the slowest.
Amar can complete the project in 32 months.
CAT 2021 Slot 1 Question 8-
Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is
A.8
B.6
C.5
D.7
Explanation

CAT 2020 Slot 3 Question 9-
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
Explanation
The contractor finishes 1.5 km in 60 days with 140 people.
That means, he finishes, 0.5 km in 20 days with 140 people.
He has 200 – 60 = 140 days left to finish the job.
Let’s say 20 days is 1 unit of time.
So the contractor finishes 0.5 km in 1 unit of time with 140 people, He has 4.5 kms to finish in 7 units of time(7 × 20 days) with n people.
The working capacity of the peopl should still be the same…
Therefore, 0.5/140 * 1 = 4.5/n * 17
n = 180.
Therefore, the contractor needs, 180 – 140 = 40 people more.
CAT 2020 Slot 2 Question 10-
John takes twice as much time as Jack to finish a job. Jack and Jim together take one-thirds of the time to finish the job than John takes working alone. Moreover, in order to finish the job, John takes three days more than that taken by three of them working together. In how many days will Jim finish the job working alone?
Explanation
John = x units/day
Jack = 2x units/day
Jim = x units/day (1/3rd of John does = 3x units, out of which jack does 2x)
Total = 4x units/day
John’s time taken = x(n+3) = 4x × n
Then n = 1 day for 4x units
For x units, Jim will take 4 days
CAT 2019 Slot 2 Question 11-
Anil alone can do a job in 20 days while Sunil alone can do it in 40 days. Anil starts the job, and after 3 days, Sunil joins him. Again, after a few more days, Bimal joins them and they together finish the job. If Bimal has done 10% of the job, then in how many days was the job done?
A.13
B.12
C.15
D.14
Explanation
Anil in one day can do th of the work
Sunil in one day can do th of the work
Anil starts the job and Sunil joins him after three days.
So, Anil would have done th of the work by the time Sunil joins
After Sunil joins, they both would be doing th of work everyday
Now, it is known that Bimal joins them after some days and finishes 10 % of the work.
Now, Anil alone had done th of the work and Bimal completes th of the work
So, in total they would have done = th of the work (is the work done by Bimal)
Remaining work = , which would be done by Anil and Sunil in 10 days.
Combining everything,
Total number of days = 3 + 10 = 13 days
CAT 2019 Slot 2 Question 12-
John gets Rs 57 per hour of regular work and Rs 114 per hour of overtime work. He works altogether 172 hours and his income from overtime hours is 15% of his income from regular hours. Then, for how many hours did he work overtime?
Explanation
If John works the same number of regular and over-time hours say ‘p’
The the income would be 57p and 114p
Let’s say that he works ‘x’ hours regular and ‘y’ hours overtime…
So, the income would be 57x and 114y
we are told that 114y is 15% of 57x
114y = 0.15 * 57x
y = 0.075x
we also know that x+y = 172
therefore, x + 0.075x = 1.075x = 172
x = 160
y = 172 – 160 = 12
Therefore, the number of hours he worked Overtime is 12.
CAT 2019 Slot 1 Question 13-
At their usual efficiency levels, A and B together finish a task in 12 days. If A had worked half as efficiently as she usually does, and B had worked thrice as efficiently as he usually does, the task would have been completed in 9 days. How many days would A take to finish the task if she works alone at her usual efficiency?
A.18
B.12
C.24
D.36
Explanation

CAT 2019 Slot 1 Question 14- Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?
Explanation
Let Machines be referred as R and men be referred as M
It is given that, three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job.
From the given data,
3M + 8R = 2 x (3R + 8M)
2R = 13M
R = M
Therefore, if two machines can finish a job in 13 days, 2 Robos can finish the job in 13 days.
CAT 2018 Slot 2 Question 15-
A tank is emptied everyday at a fixed time point. Immediately thereafter, either pump A or pump B or both start working until the tank is full. On Monday, A alone completed filling the tank at 8 pm. On Tuesday, B alone completed filling the tank at 6 pm. On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank. At what time was the tank filled on Thursday if both pumps were used simultaneously all along?
A.4 : 12 PM
B.4 : 24 PM
C.4 : 48 PM
D.4 : 36 PM
Explanation
Given that a tank is emptied everyday at a fixed time point and after that either pump A or B or both start working to fill the tank.
On Monday, A alone completed filling the tank at 8 pm.
On Tuesday, B alone completed filling the tank at 6 pm.
On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank.
We have to find at what time will the tank filled on thursday if both were used simultaneously all along
A is doing 3 hours less work on Wednesday which B completes in 2 hours therefore B = 1.5 A
⟹ nn−2
= 32
⟹ 2n = 3n – 6
⟹ n = 6
A takes 6 hours and B takes 4 hours or the tank is closed at 2 pm
When they are together open
⟹ 16
+ 14
= 2+312
⟹ Rate is 512
or they can fill the entire tank in 125
hours which is 2 hours 24 minutes
Starting from 2 pm, they fill the entire tank by 4:24 pm
Here the break through is figuring out the ratio or efficiency of the rate at which they fill is B : A = 3 : 2
The conventional way is
⟹ n−3n
+ 2n−2
= 1
n-3 hours at the rate of 1n
per hour
2 hours at the rate 1n−2
per hour
Solving this we get n = 6 and we can find solution using this n.
The question is “A tank is emptied everyday at a fixed time point. Immediately thereafter, either pump A or pump B or both start working until the tank is full. On Monday, A alone completed filling the tank at 8 pm. On Tuesday, B alone completed filling the tank at 6 pm. On Wednesday, A alone worked till 5 pm, and then B worked alone from 5 pm to 7 pm, to fill the tank. At what time was the tank filled on Thursday if both pumps were used simultaneously all along?”
Hence, the answer is 4 : 24 PM
CAT 2018 Slot 2 Question 16-
Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?
A.12
B.14.5
C.13.5
D.11
Explanation
Given that Ramesh and Ganesh can together complete a work in 16 days
After seven days of working together, Ramesh got sick and his efficiency fell by 30%.
To the original schedule of 16 days there are 9 more days and in this 9 days Ramesh fall short by 9 × 0.3x = 2.7x where x is the work done by Ramesh in a day
So the change = 2.7x (i.e. the gap because of drop in efficiency)
This 2.7x is compensated by one day of Ganesh + another 0.7 of Ramesh
2.7x = G + 0.7 x (Because the last day also he works with reduced efficiency)
2x = G
Hence Ganesh works twice as that of Ramesh.
If Ganesh had worked alone after Ramesh got sick means in the 7 days Ramesh would have completed 7/48
of the task
Ganesh on each day can do 1/24
of the task
Task to be completed by Ganesh is 41/48
completely
One day he can complete 1/24
so 41/48
× 24/1
= 20.5 days
If Ganesh had worked alone after Ramesh got sick, the no.of days needed for completing the remaining work is 20.5 – 7 = 13.5 days
CAT 2017 Slot 1 Question 17-
A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?
Explanation
Given that a person can complete a job in 120 days.
He works alone on Day 1.
On Day 2, he is joined by another person who also can complete the job in exactly 120 days.
On Day 3, they are joined by another person of equal efficiency.
Everyday a new person with the same efficiency joins the work
So by first day 1 person
Similarly by second day 2
Third day 3 and it goes on…….until it makes a total of 120
We have to find how many days are required to complete the job
So 15×16/2
= 120 [by n(n+1)/2]
So 1 + 2 + 3 + 4 …… till 15 days are required to complete this Job.
This will get completed in 15 days.
Hence 15 days are required to complete the job
CAT 2017 Slot 2 Question 18-
Amal can complete a job in 10 days and Bimal can complete it in 8 days. Amal, Bimal and Kamal together complete the job in 4 days and are paid a total amount of Rs 1000 as remuneration. If this amount is shared by them in proportion to their work, then Kamal’s share, in rupees, is
A.100
B.200
C.300
D.400
Explanation
Given that Amal can complete a job in 10 days ⟹ Rate = 1/10
Bimal can complete it in 8 days ⟹ Rate = 1/8
Amal, Bimal and Kamal together complete the job in 4 days ⟹ Rate = 1/4
Kamal’s rate of doing work is,
Amal + Bimal + Kamal = 1/4
⟹ 1/10 + 1/8+ Kamal = 1/4
⟹ Kamal = 1/4
– 1/8
− 1/10
⟹ Kamal = 10/40 – 5/40− 4/40
Kamal’s rate of doing work = 1/40
Kamal would have taken 40 days to complete the entire task.
Amal : Bimal : Kamal = 1/10 : 1/8: 1/40
= 4 : 5 : 1
Total amount of Rs.1000 is paid as remuneration
Amal : Bimal : Kamal = 4/10 : 5/10 : 1/10
Kamal’s share = 110
× 1000 = Rs.100









